Recycling Grants Expenditures
Specific Grant Expenditures Details for NEA01-01

Grant Expenditures
Year Date Amount Summary
2005 7/11/2006 $0.00 No activity in year 2005. The expansion cost $45,263.67. Therefore, $2,744.67 of bank interest was used with the grant funds to pay for the expansion and engineering cost. Check 471 on 03/10/03 for $22,817.56; check 472 on 03/28/03 for $2,500; and check 474 on 04/21/03 for $19,946.11.
2004 8/12/2005 $0.00 Expansion cost $45,263.67. Therefore, $2,744.67 of bank interest was used with the grant funds to pay for the expansion and engineering cost. Check 471 on 03/10/03 for $22,817.56; check 472 on 03/28/03 for $2,500; and check 474 on 04/21/03 for $19,946.11.
2003 9/10/2004 $0.00 Funds were expended with: check 471 March 10, 2003; check 472 March 28, 2003; check 473 April 21, 2003.
2002 7/15/2003 $42,519.00 Modification cost: $45,263.67 Grant amount: $42,519.00 Funds expended. Modifications were completed. + bank interest: $2,744.67 = $45,263.57 - $42,763.67 check 471 March 10, 2003 and check 474 April 21, 2003 to Kirk & Brazil Construction. $2500 check 472 March 28, 2003 to engineers for design plans.
2001 7/1/2002 $0.00 Funds are being held to be combined with year 2002 grants to modify existing recycling center and purchase new baler.