Permitted Facility Report
DEQ Solid Waste Management

Close this window   Print this page
Eco-Vista, LLC
Eco-Vista, LLC Tontitown Facility Class: 1 County: Washington
Permit #: 0290-S1-R4 Permit Status: Active Permit Engineer: Annette Cusher
AFIN: 72-00144 Facility Status: Open Inspector: Jason Gilkey
Contact: Ms. Jodi Reynolds-Coffelt Title: Environmental Manager Phone: (479) 699-1475
Address: 88 Joyce Lane Russellville, AR 72802 Fax:

Permitted Facility Report

Note: Click underlined Entry number for PDF copy of the original document.

<<   <  >   >> 

Letter Date/
Entry Date
Entry/ XRef Score Summary
Recs Found: 2,239
<<   <    /45  >   >> 
   
5/7/2024
5/8/2024
85508
Email from Jodi Reynolds to GB: Second Quarter of 2024 Explosive Gas Monitoring Report
4/29/2024
4/30/2024
85466
Email from Travis Doll to GWR: March 2024 Monthly Indicator Parameter Monitoring Report
4/25/2024
4/24/2024
85452
85403
Approval Letter of Construction Quality Assurance for Cell 13A Eco-Vista, LLC Class 1 Landfill
4/19/2024
4/22/2024
85442
Email from Jodi Reynolds to GB: Second Quarter 2024 Explosive Gas Monitoring Report
4/16/2024
4/18/2024
85423
Email from Jodi Reynolds to GB: Request for Two Operating Faces
4/13/2024
4/15/2024
85403
Email from Brad Fureigh to GB: Construction Quality Control and Construction Quality Assurance for Cell 13A Report
4/4/2024
4/9/2024
85358
Waste Management to SS: 2024 Financial Assurance Certificates of Insurance
3/29/2024
4/1/2024
85297
Email from Brad Fureigh to GB: 2023 Annual Engineering Inspection Report
3/26/2024
3/27/2024
85264
Email from Travis Doll to GWR: February 2024 Monthly Indicator Parameter Monitoring Report
3/19/2024
3/19/2024
85242
Email from CK to DT: Report 032460
3/18/2024
3/19/2024
85241
Email from DT to CK: Cover Pictures from March 14, 2024 and Weather Data
3/4/2024
3/7/2024
85168
Email from Jodi Reynolds to GB: Fourth Quarter 2023 Explosive Gas Monitoring Report
2/23/2024
2/26/2024
85148
Email from Travis Doll to GWR: January 2024 Monthly Indicator Parameter Monitoring Report
2/15/2024
2/15/2024
85122
Email from Steve Jett to GWR: First Half 2024 Wildcat Creek Sampling Results
1/30/2024
1/30/2024
85070
Email from Travis Doll to GWR: December 2023 Monthly Indicator Parameter Monitoring Report
1/28/2024
1/29/2024
85064
Email from Stacy Kennedy to GWR: Analytical Reports (5)
1/28/2024
1/29/2024
85067
Email from Stacy Kennedy to GWR: Analytical Reports (2)
1/28/2024
1/29/2024
85066
Email from Stacy Kennedy to GWR: Analytical Reports (4)
1/28/2024
1/29/2024
85065
Email from Stacy Kennedy to GWR: Analytical Reports (4)
1/12/2024
1/19/2024
85036
Email from Jodi Reynolds to GB: First Quarter 2024 Explosive Gas Monitoring Report
1/2/2024
1/2/2024
84982
Email from Ciara Childers Beavers to GWR: Second Half 2023 Groundwater Monitoring Report
12/29/2023
1/2/2024
84981
Email from Travis Doll to GWR: November 2023 Monthly Indicator Parameter Monitoring Report
12/28/2023
1/2/2024
84979
Email from Steve Jett to GWR: Monitoring Point Installation and Abandonment Report
11/30/2023
12/4/2023
84915
Email from Travis Doll to GWR: October 2023 Monthly Indicator Parameter Monitoring Report
11/28/2023
12/4/2023
84910
Email from Steve Jett to GWR: Updated Corrective Action Monitoring Plan
11/25/2023
11/30/2023
84899
Email from Stacy Kennedy to GWR: Analytical Reports (7)
10/26/2023
10/26/2023
84798
84782
Q3 2023 EGM Report
10/26/2023
10/31/2023
84812
Email from Jodi Reynolds to KD: Fire Notification
10/25/2023
10/27/2023
84801
Email from Travis Doll to GWR: September 2023 Monthly Indicator Parameter Monitoring Report
10/17/2023
10/19/2023
84764
Email from Brad Fureigh to AC: Eco-Vista Class 1 Landfill - Cell 13A Notification of Construction
10/2/2023
10/2/2023
84699
84235
DEQ Approval of Work Plan for Piezometer Abandonments within Document ID 84235
9/29/2023
10/23/2023
84782
Email from Jodi Reynolds to GB: 2023 Third Quarter Explosive Gas Monitoring Report
9/28/2023
10/1/2023
84695
Email from Travis Doll to GWR: August 2023 Monthly Groundwater Monitoring Report
9/26/2023
9/30/2023
84691
Email from Melissa Vaught to GWR: Revised Sampling and Analysis Plan
9/1/2023
9/5/2023
84580
Email from Steve Jett to BS: Second Half 2023 Wildcat Creek Sampling Results
9/1/2023
9/15/2023
84630
Email from Jodi Reynolds to RH: Info regarding Tracking Out from the Eco Vista Landfill
8/28/2023
8/28/2023
84489
84235
DEQ Review of Work Plan for Piezometer Abandonments & Out-of-Waste Extraction Well Relocations
8/18/2023
8/26/2023
84473
Email from Travis Doll to GWR: July 2023 Monthly Sampling Event Report
7/31/2023
7/31/2023
84389
Final Permit concerning the expansion of the Class 1 landfill and an application dated July 6, 2021
7/26/2023
7/27/2023
84400
Email from Travis Doll to GWR: June 2023 Monthly Groundwater Monitoring Report
6/28/2023
7/3/2023
84291
Email from Steve Jett to GWR: May 2023 Monthly Groundwater Monitoring Report
6/22/2023
6/26/2023
84256
Written Comments Received at Public Hearing on May 25, 2023
6/19/2023
6/19/2023
84235
Email from Steve Jett to gwreports: Work Plan for Piezometer Abandonments and Out-of-Waste Extraction Well Relocations
6/14/2023
6/15/2023
84226
Email from Travis Doll to gwreports: First Half 2023 Groundwater Monitoring Report
6/2/2023
6/2/2023
84128
83544
Acknowledgement of DFP.
5/31/2023
6/12/2023
84203
Email from Dawn Cloud to NJ: Comment on Draft Permit
5/30/2023
6/12/2023
84206
Email from Kenneth Lovett to NJ: Comment on Draft Permit
5/30/2023
5/31/2023
84086
Email from Jami Morgan to NJ: Comment on Draft Permit
5/30/2023
5/31/2023
84081
Email from Linda Carpenter to NJ: Comment on Draft Permit
5/30/2023
5/31/2023
84083
Email from Penny Baskin to NJ: Comment on Draft Permit